VESTI IZ SVETA ELESA

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Phasellus lectus magna, dictum eu nisl vitae, accumsan dapibus diam. Vestibulum consequat quam quis neque vestibulum venenatis. Nullam at euismod lectus, vitae elementum ex.

16.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG due to the maintenance work, NTC value in direction AT-SI for delivery day 18.10.2013 will be reduced to:600 MW from 00:00 to 07:00,500 MW from 07:00 to 18:00,600 MW from 18:00 to 24:00.  Read More

15.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG due to the maintenance work, NTC value in direction AT-SI for delivery day 17.10.2013 will be reduced to:600 MW from 00:00 to 07:00,500 MW from 07:00 to 18:00,600 MW from 18:00 to 24:00. Read More

14.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG due to the maintenance work, NTC value in direction AT-SI for delivery day 16.10.2013 will be reduced to:600 MW from 00:00 to 07:00,500 MW from 07:00 to 18:00,600 MW from 18:00 to 24:00.  Read More

13.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 600 MW for delivery day 15.10.2013 from 00:00 to 24:00 due to the maintenance work.  Read More

12.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 600 MW for delivery day 14.10.2013 from 00:00 to 24:00 due to the maintenance work.  Read More

11.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 750 MW for delivery day 13.10.2013 from 00:00 to 24:00 due to the maintenance work.  Read More

10.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 750 MW for delivery day 12.10.2013 from 00:00 to 24:00 due to the maintenance work. Read More

09.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 750 MW for delivery day 11.10.2013 from 00:00 to 24:00 due to the maintenance work.  Read More

08.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG due to the maintenance work, NTC value in direction AT-SI for delivery day 10.10.2013 will be reduced to:750 MW from 00:00 to 08:00,500 MW from 08:00 to 12:00,750 MW from 12:00 to 24:00.  Read More

07.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 750 MW for delivery day 9.10.2013 from 00:00 to 24:00 due to the maintenance work.  Read More

Page 274 of 331 First 272273[274]275276 Last

© 2016 ELES, ALL RIGHTS RESERVEDAAAPrivacy Policy/Authors