20.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 600 MW for delivery day 22.10.2013 from 00:00 to 24:00 due to the maintenance work. Read More

19.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 600 MW for delivery day 21.10.2013 from 00:00 to 24:00 due to the maintenance work. Read More

18.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 750 MW for delivery day 20.10.2013 from 00:00 to 24:00 due to the maintenance work. Read More

17.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 600 MW for delivery day 19.10.2013 from 00:00 to 24:00 due to the maintenance work. Read More

17.10.2013 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

16.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, allocation of intraday cross-border capacity in direction AT-SI will be stopped for delivery period 17.10.2013 from 10:00 until 21:00 due to expected high physical flows through Austrian transmission grid. Read More

16.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG due to the maintenance work, NTC value in direction AT-SI for delivery day 18.10.2013 will be reduced to:600 MW from 00:00 to 07:00,500 MW from 07:00 to 18:00,600 MW from 18:00 to 24:00.  Read More

15.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG due to the maintenance work, NTC value in direction AT-SI for delivery day 17.10.2013 will be reduced to:600 MW from 00:00 to 07:00,500 MW from 07:00 to 18:00,600 MW from 18:00 to 24:00. Read More

14.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG due to the maintenance work, NTC value in direction AT-SI for delivery day 16.10.2013 will be reduced to:600 MW from 00:00 to 07:00,500 MW from 07:00 to 18:00,600 MW from 18:00 to 24:00.  Read More

13.10.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 600 MW for delivery day 15.10.2013 from 00:00 to 24:00 due to the maintenance work.  Read More