Business User News

In the news, we notify electrical energy market participants about all important events that could impact their operations.

05.08.2016 | Business user news

We would like to inform market participants that on the request of Italian Transmission System operator TERNA, due to shorter than planned maintainance work, NTC value in direction IT-SI for delivery days 12.08.2016 will be changed to following values: New NTC values   Read More

05.08.2016 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI for delivery day 07.08.2016 will be reduced due to the expectation of high physical flows to following values:Reduced NTC values  Read More

04.08.2016 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

04.08.2016 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI for delivery day 06.08.2016 will be reduced due to the expectation of high physical flows to following values:Reduced NTC values  Read More

03.08.2016 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

03.08.2016 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI for delivery day 05.08.2016 will be reduced due to the expectation of high physical flows to following values:Reduced NTC values  Read More

03.08.2016 | Business user news

Please be informed that due to maintainance work on the Austrian System Operator APG's Scheduling system the application  will be stoped on 03.08.2016 between 22:00 and approximately till 04.08.2016 07:00.From 21:15 on and through the mentioned period day ahead and intraday schedule nominations will not be processed and no matching and confirmation will take place. Confirmed schedules with delivery hours in the above mentioned period remain unchanged.  Read More

02.08.2016 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

02.08.2016 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI for delivery day 04.08.2016 will be reduced due to the expectation of high physical flows to following values:Reduced NTC values  Read More

02.08.2016 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

Page 160 of 331 First 158159[160]161162 Last