Business User News

In the news, we notify electrical energy market participants about all important events that could impact their operations.

10.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 12.9.2013 from 00:00 to 24:00 due to the maintenance work. Read More

09.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 11.9.2013 from 00:00 to 24:00 due to the maintenance work. Read More

08.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 10.9.2013 from 00:00 to 24:00 due to the maintenance work. Read More

07.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 9.9.2013 from 00:00 to 24:00 due to the maintenance work. Read More

06.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 8.9.2013 from 00:00 to 24:00 due to the maintenance work.  Read More

05.09.2013 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

05.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 7.9.2013 from 00:00 to 24:00 due to the maintenance work. Read More

04.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 6.9.2013 from 00:00 to 24:00 due to the maintenance work. Read More

03.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 5.9.2013 from 00:00 to 24:00 due to the maintenance work.  Read More

02.09.2013 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 650 MW for delivery day 4.9.2013 from 00:00 to 24:00 due to the maintenance work. Read More